2024-12-28
Zhejiang Luhai New Energy was incorporated in April 2013 with registered capital of RMB 100 million and total project investment of RMB 795 million. Once completed, the project will run four cylindrical cell lines and two prismatic aluminium-shell cell lines with an annual capacity of 300 million Ah. Phase I finished equipment installation and commissioning in April 2014 and went into production smoothly, and has now gradually built up capacity for 70,000 to 80,000 high-energy 18650 lithium-ion cells per day.